Upper West Side#7 of 11 overall
Nov 9 – Nov 15 · overall completion, last 7 complete days
24%
▼ 1 pt vs 30-day
7-day completion by department
Manager
43%▲ 5
FOH
40%▲ 4
BOH
11%▼ 13
DOH
0%▼ 3
Weekly leadership checklists
GM · AGM · last 8 complete weeks · weakest first
| Checklist | Sep 20 | Sep 27 | Oct 4 | Oct 11 | Oct 18 | Oct 25 | Nov 1 | Nov 8 | Done |
|---|---|---|---|---|---|---|---|---|---|
| GM Premises | ✓ | ✓ | ✓ | ✓ | ✓ | ✓ | ✓ | ✓ | 100%8/8 |
| AGM Premises | ✓ | ✓ | ✓ | ✓ | ✓ | ✓ | ✓ | ✓ | 100%8/8 |
| GM Tasks | ✓ | ✓ | ✓ | ✓ | ✓ | ✓ | ✓ | ✓ | 100%8/8 |
| AGM Tasks | ✓ | ✓ | ✓ | ✓ | ✓ | ✓ | ✓ | ✓ | 100%8/8 |
| Shift | Mon7/6 | Tue7/7 | Wed7/8 | Thu7/9 | Fri7/10 | Sat7/11 | Sun7/12 | Week |
|---|---|---|---|---|---|---|---|---|
| AM Opening | ✓ | ✓ | ✓ | ✓ | ✓ | ✓ | ✓ | 100% |
| AM Closing | ✓ | ✓ | ✓ | ✓ | ✓ | ✓ | ✓ | 100% |
| PM Closing | ✓ | ✓ | ✓ | ✓ | ✓ | ✓ | ✓ | 100% |
By shift & position
Manager · last 30 days · ranked, weakest first
- AM Opening0%0/30
- PM Closing40%12/30
- AM Closing73%22/30
- On track · 90%+
- Steady · 75–89%
- Watch · 50–74%
- Behind · under 50%
- No data