Westville

Upper West Side#3 of 11 overall

Jul 17 – Jul 23 · overall completion, last 7 complete days

74%
10 pt vs 30-day

7-day completion by department

Manager

89%4

FOH

72%8

BOH

64%10

DOH

71%19

Weekly leadership checklists

GM · AGM · last 8 complete weeks · weakest first

Weekly leadership checklists over the last 8 complete weeks, weakest first.
ChecklistMay 24May 31Jun 7Jun 14Jun 21Jun 28Jul 5Jul 12Done
GM Premises
75%6/8
GM Tasks
75%6/8
AGM Premises
100%8/8
AGM Tasks
100%8/8

The week

Manager · checklists done out of expected · weakest first

← PrevFeb 21 – Mar 7Next →Latest
Manager checklist completion by shift over 7 days, weakest first.
ShiftSat2/21Wed2/25Thu2/26Sat2/28Tue3/3Wed3/4Sat3/7Week
AM Opening
0%
AM Closing
0%
PM Opening
0%
PM Closing
0%

By shift & position

Manager · last 30 days · ranked, weakest first

  • AM Opening90%27/30
  • PM Closing93%28/30
  • PM Opening93%28/30
  • AM Closing97%29/30