Westville

Dumbo#6 of 11 overall

Sep 19 – Sep 25 · overall completion, last 7 complete days

59%
▼ 12 pt vs 30-day

7-day completion by department

Manager

79%±0

FOH

60%▼ 1

BOH

69%▼ 15

DOH

29%▼ 31

Weekly leadership checklists

GM · AGM · last 8 complete weeks · weakest first

Weekly leadership checklists over the last 8 complete weeks, weakest first.
ChecklistAug 2Aug 9Aug 16Aug 23Aug 30Sep 6Sep 13Sep 20Done
GM Tasks✕✓✓✕✓✓✕✓
63%5/8
GM Premises✓✓✕✓✓✓✕✓
75%6/8
AGM Tasks✓✓✕✕✓✓✓✓
75%6/8
AGM Premises✓✓✓✓✓✓✓✓
100%8/8

The week

Manager · checklists done out of expected · weakest first

No completed days to show yet

By shift & position

Manager · last 30 days · ranked, weakest first

  • AM Closing70%21/30
  • AM Opening73%22/30
  • PM Opening83%25/30
  • PM Closing90%27/30